Al-Mahsamma Waste Water Treatment Plant

Al-Mahsama-Wastewater-Treatment-Plant-osisco-project

Case

  • The plant is to be built on an area of 150 feddans, with a capacity of 1 million cubic meters of water per day.
  • Mainly the scope work was Repairing of water tanks.

Problem

  • Water Leakage from the expansion joints, joint width= 5cm.
  • Water leakage from the concrete itself.

Solution

  • TPH Variotite was applied in the joints to make a permanent waterproofing solution.
  • Variotite has a setting time of 10 secs, elongation up to 750%, strong Adhesion to concrete.
  • PUR-O-Stop 1 Component Flexible polyurethane foam was applied to the tanks concrete body.
  • Both Materials used are Eco-friendly & Permeant Waterproofing Material.
Feed Back

What Our Clients Sayes

Lorem ipsum dolor sit amet, consetetur sadipscing elitr, sed diam nonumy eirmod tempor invidunt ut labore et dolore magna aliquyam erat, sed diam voluptua. At vero eos et accusam et justo duo dolores et ea rebum. Stet clita kasd gubergren, no sea takimata sanctus est Lorem ipsum dolor sit amet. Lorem ipsum