Elsewedy Electric Tunnel (underground Tunnel) – New Capital

[rank_math_breadcrumb]
Elsewedy-Electric-Tunnel-(underground-Tunnel)-–-New-Capital

Case

  • The project includes engineering, design, fabrication, site testing, and commissioning to connect the main 3 substations at the New Administrative Capita with a total route length 17 KM

Problem

  • Water Leakage from the expansion joints & Kicker due to Bad Waterproofing and break of water pipe.
  • Joint Width=5cm.

Solution

  • TPH Variotite was applied in the joints to make a permanent waterproofing solution.
  • Variotite has a setting time of 10 secs, elongation up to 750%, strong Adhesion to concrete.
  • Rubbertite was applied to the kickers.
  • PUR-O-Stop 1 Component Flexible polyurethane foam was applied to reduce water flow.
  • Both Materials used are Eco-friendly & permanent Waterproofing Materials.
Feed Back

What Our Clients Sayes

Lorem ipsum dolor sit amet, consetetur sadipscing elitr, sed diam nonumy eirmod tempor invidunt ut labore et dolore magna aliquyam erat, sed diam voluptua. At vero eos et accusam et justo duo dolores et ea rebum. Stet clita kasd gubergren, no sea takimata sanctus est Lorem ipsum dolor sit amet. Lorem ipsum